Bulk Carrier
Jul 2023
Completed
Eastern Star
Chittagong Port
Emergency propeller replacement and shaft alignment for bulk carrier.
Need Similar Service?
Get expert consultation for your vessel repair needs
100%
On-Time Delivery
98%
Quality Score
24
Team Size
95%
Efficiency

Project Duration
14 days
Completed: July 15, 2023
Vessel Specifications
Length Overall
190m
Gross Tonnage
40,000 DWT
Flag State
Singapore
Vessel Type
Bulk Carrier
Services Provided
Propeller Replacement
Shaft Alignment
Underwater Inspection
Project Timeline
Initial Inspection
CompletedDay 1-3
Repair Planning
CompletedDay 4-7
Material Procurement
CompletedDay 8-14
Repair Execution
CompletedDay 15-40
Quality Testing
CompletedDay 41-43
Final Inspection
CompletedDay 44-45
Certified & Compliant
All repair works completed in full compliance with international maritime standards and safety regulations. Quality assurance certified by classification society.