LNG Carrier
Jan 2023
Completed

Gas Transporter

Chittagong Port

Comprehensive 5-year special survey including tank inspection and certification.

Need Similar Service?

Get expert consultation for your vessel repair needs

100%

On-Time Delivery

98%

Quality Score

24

Team Size

95%

Efficiency

Gas Transporter

Project Duration

65 days

Completed: January 31, 2023

Vessel Specifications

Length Overall

280m

Gross Tonnage

125,000 m³

Flag State

Marshall Islands

Vessel Type

LNG Carrier

Services Provided

Special Survey
Tank Inspection
Class Certification
Gas Systems

Project Timeline

Initial Inspection

Completed

Day 1-3

Repair Planning

Completed

Day 4-7

Material Procurement

Completed

Day 8-14

Repair Execution

Completed

Day 15-40

Quality Testing

Completed

Day 41-43

Final Inspection

Completed

Day 44-45

Certified & Compliant

All repair works completed in full compliance with international maritime standards and safety regulations. Quality assurance certified by classification society.